Essay
The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:

Verified
(a)J; (b)20; (c)A-B-...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: The PERT pessimistic time estimate is an
Q31: One responsibility of a project manager is
Q37: WBS stands for which of the following
Q75: Analysis of a PERT problem shows the
Q89: The fundamental difference between PERT and CPM
Q98: The project organization works best when which
Q102: The network below represents a project being
Q103: Consider the network presented in the following
Q113: _ is the amount of time an
Q114: A simple CPM network has five activities,A,B,C,D,and