Multiple Choice
The beta distribution is used in project management to:
A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified