A Work Center Had Planned Outputs of 10,15,13,and 20 Hours

Question 100

Multiple Choice

A work center had planned outputs of 10,15,13,and 20 hours with actual outputs of 12,14,13,and 18 hours.What is the cumulative deviation in output?


A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information

Correct Answer: