Multiple Choice
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract puts in a due date of 80 weeks, what is the probability that they will have to pay a penalty?
A) 0
B) 1.000
C) 0.500
D) 1/8
Correct Answer:

Verified
Correct Answer:
Verified
Q129: The time required to travel downtown at
Q130: A company is considering producing two new
Q131: Disco Fever is randomly found in one
Q132: Suppose that 10 golfers enter a tournament
Q133: The number of cell phone minutes used
Q135: What is the probability that F is
Q136: Queuing Theory makes use of the<br>A)normal probability
Q137: Given two statistically independent events (A,B), the
Q138: Although one revision of prior probabilities can
Q139: The number of calls received by call