Multiple Choice
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
Correct Answer:

Verified
Correct Answer:
Verified
Q32: Table 11-4<br>The following represents a project with
Q33: Table 11-5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-5
Q34: The crash time of an activity represents<br>A)the
Q35: Table 11-4<br>The following represents a project with
Q36: Given:<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Given:
Q38: PERT stands for Probabilistic Evaluation and Review
Q39: A small software development project has four
Q40: The project described by <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="The
Q41: Given (Time in weeks):<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Given
Q42: In a PERT analysis, how is the