Multiple Choice
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Determine the minimum cost project factoring in both the costs of expediting and the opportunity cost.What is the duration of the overall minimum cost project?
A) 49 weeks
B) 48 weeks
C) 47 weeks
D) 46 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q68: Gantt charts contain information about the time
Q69: Table 11-8<br>A mad scientist has identified the
Q70: Table 11-8<br>A mad scientist has identified the
Q71: Table 11-8<br>A mad scientist has identified the
Q72: Table 11-5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-5
Q74: Table 11-2<br>The following represents a project with
Q75: The longest time path through a PERT/CPM
Q76: An alternative approach to project crashing is
Q77: CPM is the acronym for what?
Q78: PERT is the acronym for what?