A Goal Programming Problem Had Two Goals (With No Priorities

Question 50

Multiple Choice

A goal programming problem had two goals (with no priorities assigned) .Goal number 1 was to achieve a cost of $3,600 and goal number 2 was to complete the task in 400 hours or fewer.The optimal solution to this problem resulted in a cost of $3,600 and a completion time of 420 hours.What was the value for the objective function for this goal programming problem?


A) 400
B) -400
C) 20
D) 0