Figure 12-1 Figure 12-1   -Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place? A)  The critical path will change to: A-C-B-D-E-F-H. B)  Activity F will be delayed by four days. C)  Activity E will be delayed by four days. D)  Activity G will be delayed by four days. E)  None of the above
-Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place?


A) The critical path will change to: A-C-B-D-E-F-H.
B) Activity F will be delayed by four days.
C) Activity E will be delayed by four days.
D) Activity G will be delayed by four days.
E) None of the above