Multiple Choice
A goal programming problem had two goals (with no priorities assigned) .Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory.The optimal solution to this problem resulted in a profit of $2,300 and no idle time.What was the value for the objective function for this goal programming problem?
A) 2300
B) 100
C) -100
D) 0
E) None of the above