Multiple Choice
A goal programming problem had two goals (with no priorities assigned) .Goal number 1 was to achieve a profit of $3,600 and goal number 2 was to have no wasted material.The optimal solution to this problem resulted in a profit of $3,300 and no wasted material.What was the value for the objective function for this goal programming problem?
A) 300
B) -300
C) 3300
D) 0
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q3: There is no general method for solving
Q54: The constraint X<sub>1</sub> + X<sub>2</sub> ≤ 1
Q63: A quadratic programming problem involves which of
Q64: A goal programming problem had two goals
Q66: Another name for a 0-1 variable is
Q67: Table 10-5<br>Maximize Z = 34 X<sub>1</sub> +
Q69: An integer programming (maximization)problem was first solved
Q71: Goal programming and linear programming differ in
Q72: According to Table 10-6,how is the constraint
Q73: The following <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="The following