    A Material Requirements Planning (MRP)system
Solved

A Material Requirements Planning (MRP)system

Question 2

Question 2

Multiple Choice

A material requirements planning (MRP) system:


A) controls the "A" items.
B) reduces inventory.
C) is easily carried out without technology.
D) requires exploration of the bill of material as the basis of planning.
E) is essential for operating a JIT system.

Correct Answer:

verifed

Verified

Related Questions

Q1: "A" items in ABC analysis are:<br>A)reviewed infrequently.<br>B)normally

Q3: When a retailer uses daily sales of

Q4: Continuous Planning,Forecasting and Replenishment (CPFR)generates the most

Q5: The demand for a particular service may

Q6: A reduction in set-up costs and time

Q7: The following cost is not a carrying,holding,or

Q8: Capacity requirements planning (CRP):<br>A)uses ABC analysis as

Q9: On an annual requirement of 100 items

Q10: Decoupling inventories are carried:<br>A)to cover a well-defined

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines