Multiple Choice
Which of the following projects is the riskiest?
A) a project that managers are concerned will affect their roles and job descriptions
B) a project that requires technical expertise that your firm's IT employees do not have
C) a project that has a strict deadline, or sales will suffer
D) a project that will automate many clerical duties