In ____, the Objective Is to Maximize the Number of Functional

Question 6

Multiple Choice

In ____, the objective is to maximize the number of functional person-hours applied to work on projects and minimize the unapplied time.


A) an autonomous project organizational structure
B) a functional organizational structure
C) a matrix organizational structure
D) a project management office