Multiple Choice
If actual progress falls behind planned progress or unexpected events occur,
A) the project team should be on alert for future needs to accelerate tasks.
B) the project manager should take immediate action.
C) the project should be allowed to self correct.
D) other tasks will finish in less time than planned so the delay will balance.
Correct Answer:

Verified
Correct Answer:
Verified