Multiple Choice
Which of the following would not be a closing action for a project?
A) Collecting and making final payments.
B) Conducting a post-project evaluation.
C) Organizing and archiving project documents.
D) Negotiating the project contract.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q19: Just as important as having the internal
Q20: Projects also can be terminated by the
Q21: During project closing, the project team or
Q22: Projects can be terminated by the sponsor
Q23: During the post-project meeting with the customer,
Q25: The project manager should prepare a written
Q26: At the _ meeting with the project
Q27: Which of the following is the least
Q28: The type of questions the project manager
Q29: At the close of the project, the