Multiple Choice
The purpose of identifying and documenting lessons learned is to
A) use proprietary knowledge gained in the project to obtain funding from the client's competition.
B) determine what team members are the best to have on the team.
C) create a database of information
D) capitalize on the knowledge and experience gained on the project to improve future project performance.