Multiple Choice
A defined set of actions to prevent or reduce the likelihood of occurrence or the impact of risk is the
A) risk assessment matrix
B) the action trigger
C) risk identification brainstorming session
D) risk response plan
Correct Answer:

Verified
Correct Answer:
Verified