Multiple Choice
The trigger point in the risk response plan is when the project team should
A) implement the action plan for each risk.
B) stop working on the project because it cannot be completed.
C) avoid the risk by moving onto the next activity.
D) brainstorm for ideas on how to manage the risk.
Correct Answer:

Verified
Correct Answer:
Verified