The possible response plan for vendor delay in delivery of critical equipment is
A) check the order status one week before delivery needed.
B) project task completion delayed until equipment arrives.
C) contact secondary vendor to supply the part.
D) financial loss due to the delay.
Correct Answer:

Verified
Correct Answer:
Verified