Multiple Choice
Calculate the forecasted cost at completion if the cumulative actual cost is $10,000 and the re-estimate of remaining work to be performed is $5,000.
A) FCAC = $5,000
B) FCAC = $15,000
C) FCAC = 2
D) FCAC = 0.5
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q27: The positive cost variance means<br>A) more money
Q28: When the budgets for all the work
Q29: Costs related to _ are for outsourced
Q30: _ is the value of the work
Q31: A third method for determining the forecasted
Q33: The earned value is<br>A) the budgeted cost
Q34: There are two approaches to establishing the
Q35: The cumulative earned value for each work
Q36: Earned value, the value of _, is
Q37: Travel costs in the project costs estimate