Multiple Choice
The cumulative budgeted cost is
A) the aggregate estimated costs of all the activities.
B) the amount budgeted to accomplish the work scheduled to a point in time in the project.
C) the committed costs for an activity.
D) the sum of all the funds expended to a point in time in the project.
Correct Answer:

Verified
Correct Answer:
Verified