Multiple Choice
Activities drawn in a serial relationship illustrate a
A) resource constraint among the activities.
B) loop format of scheduling the project.
C) laddering format of scheduling the project.
D) technical constraint among the activities.
Correct Answer:

Verified
Correct Answer:
Verified