Multiple Choice
Earliest start time (ES) is the earliest time at which a specific activity can begin
A) calculated on the basis of the project estimated start time and the estimated durations of preceding activities.
B) calculated on the basis of the project estimated finish time and the estimated durations of preceding activities.
C) calculated on the basis of the project estimated start time and the estimated durations of succeeding activities.
D) calculated on the basis of the project estimated start time and the estimated durations of approaching activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q95: A Gantt chart is the often the
Q96: The facilitator for the Scrum development process
Q97: Total slack is calculated by _.<br>A) subtracting
Q98: It is necessary to monitor the progress
Q99: Calculate the latest finish for Task B
Q101: This longest path in the overall network
Q102: The amount of slack should determine the
Q103: The estimated duration for each activity is
Q104: For large projects that involve several hundred
Q105: Total slack for the project is the