Multiple Choice
The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?
A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 16 days slack.
D) Positive 3 days slack.