Multiple Choice
The activity bars in a bar chart are drawn in proportion to
A) the amount of slack for each activity.
B) the number of resources assigned to the activity.
C) the cost of the activity.
D) the estimated durations of each activity.
Correct Answer:

Verified
Correct Answer:
Verified