Multiple Choice
The ____ states the specific deliverable that is expected to be completed from the work activities associated with each lowest level-work package.
A) WBS in an indentured list format
B) project scope in a hierarchical graphic chart format
C) responsibility assignment matrix
D) network diagram
Correct Answer:

Verified
Correct Answer:
Verified