Multiple Choice
To draw a ____, start by drawing the activities in boxes in their logical sequence and connecting them with arrows to show the required dependent relationships, as the project should be performed from start to completion.
A) work breakdown structure
B) responsibility assignment matrix
C) acceptance criteria chart
D) network diagram
Correct Answer:

Verified
Correct Answer:
Verified