Multiple Choice
The ____ is a communication tool for the project team because it shows who is responsible for each activity and how each person's work fits into the overall project.
A) work breakdown structure
B) project scope statement
C) responsibility assignment matrix
D) network diagram
Correct Answer:

Verified
Correct Answer:
Verified
Q55: An activity does not necessarily require the
Q56: When all the detailed activities have been
Q57: Using the work breakdown structure, the individual
Q58: The work breakdown structure is a structural
Q59: It might not be possible to define
Q61: _ in a network diagram will allow
Q62: Draw network diagram for the following project.<br>Activity<br>Immediate
Q63: The agreed-upon project scope document establishes the
Q64: The _ may need to describe certain
Q65: The quality plan may also state that