Multiple Choice
In the network diagram for the following list, what activity immediately follows activity B? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
D
F
D
G
E,F
H
G
A) A
B) D
C) C
D) none, B is the starting activity
Correct Answer:

Verified
Correct Answer:
Verified