    In the Network Diagram for the Following List, What Activity
Solved

In the Network Diagram for the Following List, What Activity

Question 148

Question 148

Multiple Choice

In the network diagram for the following list, what activity immediately follows activity E? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
D
F
D
G
E,F
H
G
​


A) D
B) F
C) G
D) H

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q143: A(n)_ is defined as a piece of

Q144: The _ is a roadmap that displays

Q145: Expected benefits, which will result from implementation

Q146: The project scope document is valuable for

Q147: It is common to progressively elaborate the

Q149: The _ may include a high-level WBS

Q150: It is important to plan for _

Q151: The project objective is usually defined in

Q152: Having a written quality plan at the

Q153: The work packages are at a level

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines