Multiple Choice
The project scope document contains
A) many of the items in the project charter in greater detail.
B) detailed information about the tasks in the work breakdown structure.
C) a list of changes that are acceptable to be made on the project.
D) elaboration of the near-term and long-term tasks.
Correct Answer:

Verified
Correct Answer:
Verified