Multiple Choice
When making contingency estimates, the contractor should
A) estimate the amount to mitigate high impact and probable issues.
B) include an amount for each issue that has high impact.
C) include a small amount for each possible issue.
D) heavily pad the estimates to include every issue.
Correct Answer:

Verified
Correct Answer:
Verified