Multiple Choice
Total dollar value approach for calculating the win ratio gives
A) equal weight to proposals with larger dollar amounts.
B) more weight to proposals with larger dollar amounts.
C) equal weight to all proposals.
D) less weight to proposals with larger dollar amounts.
Correct Answer:

Verified
Correct Answer: