The new employees are expected to receive $13 million of Fast Start training that will be provided by a state workforce development grant.This is an example of the ____ in a project charter.
A) acceptance criteria
B) key assumptions
C) project description
D) success criteria and expected benefits
Correct Answer:

Verified
Correct Answer:
Verified