Multiple Choice
___ will be used by the customer to evaluate proposals from competing contractors in order to select the one to perform the project.
A) Evaluation criteria
B) Format instructions
C) Due date timelines
D) Progress payments
Correct Answer:

Verified
Correct Answer:
Verified