Multiple Choice
The initiating phase of the project life cycle starts with
A) evaluating potential projects and deciding which should go forward.
B) recognizing a need, problem or opportunity for which a project is identified.
C) developing a set of criteria to evaluate projects.
D) listing assumptions that will be used.
Correct Answer:

Verified
Correct Answer: