Multiple Choice
A ____ is a hierarchical tree of work elements or items accomplished or produced by the project team during the project.
A) work load structure
B) project breakdown diagram
C) work breakdown structure
D) baseline plan
Correct Answer:

Verified
Correct Answer:
Verified