    A ____ Is a Hierarchical Tree of Work Elements or Items
Solved

A ____ Is a Hierarchical Tree of Work Elements or Items

Question 84

Question 84

Multiple Choice

A ____ is a hierarchical tree of work elements or items accomplished or produced by the project team during the project.


A) work load structure
B) project breakdown diagram
C) work breakdown structure
D) baseline plan

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q79: The types and quantities of resources to

Q80: Constraints for a project are<br>A) schedule, budget,

Q81: The list that includes key contact information,

Q82: The outcome of a project is a

Q83: An important task to complete during the

Q85: Which of the following is an example

Q86: The stakeholder register is a convenient tool

Q87: The project objective requires completing the project

Q88: Once the project has started, unforeseen circumstances

Q89: The project objective is usually defined in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines