Multiple Choice
The key to effective ____ is measuring actual progress and comparing it to planned progress on a timely and regular basis, and taking corrective action immediately if necessary.
A) project planning
B) work breakdown
C) project control
D) quality efficiency
Correct Answer:

Verified
Correct Answer: