The Performing Phase of the Project Life Cycle Ends When

Question 73

Multiple Choice

The performing phase of the project life cycle ends when


A) all the tasks for the project are complete.
B) all the budget for the project is expended.
C) the sponsor accepts the project deliverables.
D) no changes are necessary to the baseline plan.