Multiple Choice
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date,what due date (project week #) should be negotiated?
A) 81.28
B) 92.8
C) 81.82
D) .81954
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q48: The F statistic is the ratio of
Q61: Stating that two events are statistically independent
Q92: Given two statistically dependent events (A,B), the
Q113: Drivers arrive at a toll booth at
Q116: A discrete random variable has a mean
Q117: List the parameter(s)of the Poisson distribution.
Q119: Suppose that 10 golfers enter a tournament
Q121: The probability,P,of any event or state of
Q122: The exponential distribution often describes _.
Q123: At a university with 1,000 business majors,there