Multiple Choice
CPM
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q75: The longest time path through a PERT/CPM
Q77: CPM is the acronym for what?
Q111: In a PERT network,the earliest (activity)start time
Q112: Table 11-3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-3
Q114: Table 11-1<br>The following represents a project with
Q115: Table 11-2<br>The following represents a project with
Q117: The expected time in PERT is<br>A)greater than
Q118: Shortening a project is called crashing.
Q120: Draw the PERT network associated with the
Q121: The process of smoothing out the utilization