Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 13 days respectively,compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified