menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management Study Set 2
  4. Exam
    Exam 11: Project Management
  5. Question
    Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 1,9,and
Solved

Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 1,9,and

Question 81

Question 81

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 1,9,and 23 days respectively,compute the PERT expected activity time for this activity.


A) 10
B) 12
C) 9
D) 11
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q64: CPM is a probabilistic analysis of managing

Q76: Managers use the network analysis of PERT

Q78: Given the following small project,the critical path

Q79: PERT/Cost allows a manager to do which

Q80: Activity D of a project has a

Q82: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="The

Q83: The critical path of a network is

Q84: The work breakdown structure involves identifying the

Q86: Using the data in Table 11-1,compute the

Q139: A PERT/CPM network is a graphical display

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines