Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 1,9,and 23 days respectively,compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified