Multiple Choice
Table 11-4
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-4,what is the latest possible time that C may be started without delaying completion of the project?
A) 0
B) 4
C) 8
D) 10
E) None of the above
Correct Answer:

Verified
Correct Answer: