Solved

Table 11-4 The Following Represents a Project with Known Activity Times.All Times

Question 122

Multiple Choice

Table 11-4
The following represents a project with known activity times.All times are in weeks. Table 11-4 The following represents a project with known activity times.All times are in weeks.   -Using the data in Table 11-4,determine the latest time activity A can be started without delaying the project completion. A) 4 B) 3 C) 8 D) 6 E) None of the above
-Using the data in Table 11-4,determine the latest time activity A can be started without delaying the project completion.


A) 4
B) 3
C) 8
D) 6
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions