Multiple Choice
Table 11-4
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-4,determine the latest time activity A can be started without delaying the project completion.
A) 4
B) 3
C) 8
D) 6
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified