Figure 11-1 -Given the Network Shown in Figure 11-1,assume That Completion of That

Question 35

Multiple Choice

Figure 11-1 Figure 11-1   -Given the network shown in Figure 11-1,assume that completion of B is delayed by two days.What happens to the project? A) The critical path is extended by two days. B) The start of activity F is delayed by two days. C) The start of activity E is delayed by two days. D) All of the above E) None of the above
-Given the network shown in Figure 11-1,assume that completion of B is delayed by two days.What happens to the project?


A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above

Correct Answer: