Multiple Choice
Figure 11-1
-Given the network shown in Figure 11-1,assume that completion of B is delayed by two days.What happens to the project?
A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q30: The critical path of a network is
Q31: Table 11-3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-3
Q32: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1
Q33: In PERT,the most likely completion time of
Q34: Given (Time in weeks): <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Given
Q37: Given an activity's optimistic,most likely,and pessimistic time
Q38: Which of the following is not a
Q39: PERT assumes that the total completion time
Q40: Development of a new deluxe version of
Q58: Gantt charts and PERT diagrams provide the