Multiple Choice
Table 10-5
Maximize Z = 34 X1 + 43 X2 + 29 X3
Subject to: 5 X1 + 4 X2 + 7 X3 ≤ 50
1 X1 + 2 X2 + 2 X3 ≤ 16
3 X1 + 4 X2 + 1 X3 ≤ 9
all Xi are integer and non-negative
Final Integer Solution: Z = 208
Decision
Variable Solution
X1 1
X2 0
X3 6
-Table 10-5 represents a solution for an integer programming problem.If one uses the optimal solution presented,how much slack is there in the first equation?
A) 0 units
B) 5 units
C) 3 units
D) 2 units
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Smalltime Investments Inc.is going to purchase new
Q22: Define quadratic programming.
Q26: We do not have a general method
Q28: Which of the following is not considered
Q29: Table 10-3<br>A company has decided to use
Q30: Table 10-1<br>A company has decided to use
Q32: Agile Bikes has manufacturing plants in Salt
Q33: Table 10-2<br>Maximize Z = 34 X<sub>1</sub> +
Q33: A 0-1 programming representation could be used
Q34: Table 10-6<br>The profit function for a set