Question 31

Multiple Choice

Use the following information to answer questions 13 - 15
The following data is on two one period capital projects. Use the following information to answer questions 13 - 15 The following data is on two one period capital projects.   -What is the standard deviation of probable cash flows from each project? A)  A = 159.69, B = 98.49 B)  A = 223.83, B = 139.28 C)  A = 274.22, B = 170.59 D)  A = 316.54, B = 196.98 E)  A = 354.11, B = 220.22
-What is the standard deviation of probable cash flows from each project?


A) A = 159.69, B = 98.49
B) A = 223.83, B = 139.28
C) A = 274.22, B = 170.59
D) A = 316.54, B = 196.98
E) A = 354.11, B = 220.22