Pronto Delivery is contemplating an investment in a delivery truck. The estimate of the project's price is $22,000. The delivery truck will have a life of 5 years and have a salvage value of $2,000. Annual net cash flows from the five years of operations are expected to be $6,000. If Pronto's applicable discount rate is 10%, what is the net present value of this project? Is the project acceptable?
A) NPV = -$1,986.60 and is unacceptable
B) NPV = -$1,986.60 and is acceptable
C) NPV = $1,986.60 and is unacceptable
D) NPV = $1,986.60 and is acceptable
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q29: Afterthought Construction Co. is about to sell
Q30: The process of computing the value of
Q31: An annuity is a constant amount payable
Q32: In determining the price or initial cash
Q33: Pave-It, Inc. is trying to decide whether
Q35: Discounting is the process of computing the
Q36: A project has an anticipated stream of
Q37: A project has an anticipated stream of
Q38: The internal rate of return IRR) for
Q39: The present value of a future payment