Question 99

Multiple Choice

Which of these concerns does NOT belong in the assessment of team performance in a project final report?


A) Were the stakeholder's concerns addressed?
B) Were the best people in the organization selected to work on this project?
C) How were our project team members trained for their duties?
D) Does the project manager have the ability to evaluate worker performance?